top of page

WATABEAG LAKE DAM REPLACEMENT

CONSTRUCTION OF CUT-OFF WALLS
Concrete forming, placement, finishing and curing of two cut-off walls.

CONSTRUCITON OF WINGWALLS
Concrete forming, placement, finishing and curing of two wingwalls 6m high.

CONSTRUCTION OF OGEE WEIR
Concrete forming, placement, finishing and curing of ogee wier.
Timeline: 2014 to 2015
Location: Matheson, Ontario
Description:
Replacement of the Watabeag Lake Dam included the construction of a by-pass channel to divert water from Watabeag Lake around the construction limits, construction of a new gravity dam with sheet pile cut-off wall, demolition of the existing dam, and landscaping restoration.
bottom of page